Cogent link ETA

Target date for setup is 28th of June, but it's not certain. Might take couple weeks from that before things are operational. After that is operational we will be building nodes up as fast as we can, and new orders for Super100 series will be setup on our own machines. First migrations will be 2009+ Starter as for that we can utilize 2nd hand ... Read More »

20th Jun 2013
Colocation agreement signed

Colocation agreement has been signed and management network setup. Tomorrow we will finish setting up the necessary access cards, and after mid summer festivities we will start to rack some servers. Cogent link is expected to be up by 1st of July if timetables hold, there is a 3rd party which provides the transport from the teleroom we connect ... Read More »

19th Jun 2013
Colocation progress update

We should be getting the keys, contracts etc. done within a couple of days. A lot of hardware is arriving from a lot of different places, couple storage servers has been built so far, and misc servers are lying around. Decided to do a nice upgrade to the SAN plans, we acquired several Cisco switches to act as SAN core, each switch has a ... Read More »

19th Jun 2013
Good news about colocation.

Good news!

We are getting keys to the place finally next week and are going to start setting things up.

Routing and networking setup has to be done prior to 10.7 because the network expert is about to leave for vacation then, so we are hurrying up our schedule somewhat.

 

14th Jun 2013