Transit up tomorrow

Our first transit link should be up and operational tomorrow. Our IP Block got assigned already. Netboot/iSCSI boot is still undone, but first storage brick is now stable and final configuration. i3s require 19VDC power input, a oversight in design, it was assumed they have wide input as well, so these will be delayed until late next week to get ... Több... »

4th Júl 2013
Getting your own DC running: Lots of unexpected things

When you are doing a build out like ours - so many new things, and taking certain things to extremes there is bound to be unexpected things happening. After several days of issues with a storage brick we noticed the SATA Raid controller was not compatible with this specific SSD model and make. Then basic SATA power connectors failing one after ... Több... »

3rd Júl 2013
Colocation: Cogent port assigned, PtP remains to be done, SAN almost complete

SAN is almost complete now, some configurations remain to be done, but physical layer is complete. Cogent assigned today our 10Gbase-LR port and are waiting for demarcation information, after that, PtP connection between the buildings is done and we can setup the public network. Further, we developed our own temperature & climate monitoring ... Több... »

1st Júl 2013
Upgrading to PDS14

If you have older generation PDS, or other dedicated server you may upgrade to it, the process is as follows: - order and pay the new server- Once server is setup we will adjust your service due date accordingly- You may now migrate over to the new one, or we can attempt a mirror copy- Once migrated, you may opt for prorata refund or days ... Több... »

1st Júl 2013