Espoo to Helsinki Datacenter Move: Finished (nearly)

Espoo to Helsinki datacenter move has been finished, all production servers has been moved and all but 1 are online. The last remaining node will be repaired and brought online tomorrow.

21st Márc 2016
Espoo datacenter move: Going ahead on schedule.

Espoo datacenter move will begin 10:30GMT/11:30 CET on schedule.

Expecting to have all servers online by end of the day.

21st Márc 2016
Espoo datacenter move schedule

It has been scheduled for Monday 10:00 GMT.

Several nodes will be moved upfront around 09:00 GMT, final tests will be done around 10:00 GMT at which time rest off the nodes will be shutdown at Espoo before move to Helsinki.
Expecting nodes to start coming online roughly around 16:00-17:00 GMT until finishing around 22:00 GMT.

19th Márc 2016
Espoo: Transit upgraded

Transit has been upgraded on the 1st by additional 30%.

Looks like this is not sufficient however, we will do another upgrade 1st of April.

8th Márc 2016